COUNCIL UPDATE
I. Construction Progress/Schedule
The
prime Contractor has completed their contract-required work for 2007
construction season with the exception of the remaining temporary and permanent
turf re-establishment which should be completed by
Mailboxes, signage, wood fencing, temporary erosion control, traffic control signage, and general site cleanup should also be completed November 30. The Contractor has also removed the construction trailers from the site.
We
anticipate the Contractor to commence work in late April with bituminous paving
of
1.
Bridge
The bridge is substantially completed with bridge lighting and painting to be completed in spring 2008 due to weather conditions this fall.
- Metal railing.................................................................................... Completed
- Bridge lighting............................................................................... Spring 2008
- Bridge painting.............................................................................. Spring 2008
2.
Work is completed with exception of seasonal landscaping and final wearing course.
- Landscaping (seasonal planting)..................................................... Spring 2008
- Final Wearing Course................................................................... Spring 2008
3.
Work
is completed with exception of one driveway that will be completed next
spring. Wood fencing, mailboxes, and
final cleanup should be substantially complete by the
- Sodding.................................................................................... Completed
- Landscaping (seasonal planting)............................................... Spring 2008
- Final Wearing Course............................................................. Spring 2008
Work is completed for this year, and the roadway is reopened to traffic. The temporary park access route will be closed.
- Roadway Paving ........................................................ Reopened to Traffic
- Temporary Turf and Erosion Control Establishment............ Late November
- Sodding.................................................................................. Spring 2008
- Trail and Sidewalk.................................................................. Spring 2008
- Landscaping (seasonal plantings)............................................. Spring 2008
- Final Wearing Course............................................................. Spring 2008
4.
Work on
- Roadway Embankment and Pond Construction............................... Completed
- Turf and Erosion Control Establishment........................... Late November 2007
- Concrete Curb and Gutter............................................................ Spring 2008
- Roadway Paving........................................................................... Spring 2008
- Sodding........................................................................................ Spring 2008
- Landscaping................................................................................. Spring 2008
- Final Wearing Course................................................................... Spring 2008
5.
The Contractor has completed the remaining underground utilities and roadway paved and reopened to traffic. Trail and landscaping will be completed in spring 2008.
- Roadway Paving.............................................................. Reopened for Traffic
- Turf......................................................................................... Late November
- Sodding........................................................................................ Spring 2008
- Landscaping................................................................................. Spring 2008
- Final Wearing Course................................................................... Spring 2008
6.
All of the underground utility work and roadway have been completed. The roadway is paved and reopened to local traffic. The remaining sidewalk and retaining wall will be completed in the spring.
- Roadway and Driveways Paved........................................ Reopened to Traffic
- Erosion Control and Temporary Turf............................... Late November 2007
- Sodding........................................................................................ Spring 2008
- Sidewalk...................................................................................... Spring 2008
- Final Wearing Course................................................................... Spring 2008
7.
The
sanitary sewer work east of Hwy. 169 started on October 1 and will be completed
by
- Roadway Patched and Reopened.................................................... Completed
- Temporary Turf Reestablished............................................... By November 30
- Sidewalks..................................................................................... Spring 2008
- Seal Coat and Striping.................................................................. Spring 2008
II. Project Success/Issues
1.
Success
-
- French Lake Terrace Pond has recovered.
-
Cobblestone
- All City sewer, watermain, and storm sewer work completed.
- All MCES sanitary sewer work completed.
- Bridge complete with exception of lighting and painting.
- Dewatering completed and removed.
- All temporary water services removed.
2.
Issues/Concerns
-
Currently, three residential claims unresolved:
a.
b.
foundation cracks
c.
-
-
III. Contract
Status/Changes
1.
Contract
Changes
- Change Order No. 3 – Total pedestrian Signal Painting, and miscellaneous lighting repairs being finalized.
a. City - $3,199.22
b. County - $14,133.63
- Change Order No. 4, December. Fuel tank, miscellaneous storm sewer, water service connections, and MCES extra work approximately $71,000.
a. City
anticipated $22,400 +
b. County anticipated $16,300 +
c. MCES anticipated $32,500 +
2.
Contract
Completion
- Construction costs paid through October 31 = $11.63 million.
- Anticipated construction costs spent through November = $12.63 million spent.
-
Anticipated October through December construction costs.
a. November – $1.0 million
b. December – $0.2 million
c. Spring 2008 – $2.0 million
IV. Project
Web Page Update Reminder
V. Questions/Answers