HAYDEN LAKE, TILDEN AVENUE, CHAMPLIN DRIVE

ROAD IMPROVEMENTS

COUNCIL UPDATE

November 26, 2007

 

I.       Construction Progress/Schedule

The prime Contractor has completed their contract-required work for 2007 construction season with the exception of the remaining temporary and permanent turf re-establishment which should be completed by November 30, 2007.  Not all of the yards will be able to be sodded this year, and they will, however, be covered with straw mulch for temporary erosion control.

 

Mailboxes, signage, wood fencing, temporary erosion control, traffic control signage, and general site cleanup should also be completed November 30.  The Contractor has also removed the construction trailers from the site.

 

We anticipate the Contractor to commence work in late April with bituminous paving of Tilden Avenue and the final lift of pavement to be completed by mid-June of 2008.  The contract requires all work to be completed by July 1, 2008 with all turf and landscaping items completed by June 13, 2008. 

 

1.                  Bridge

The bridge is substantially completed with bridge lighting and painting to be completed in spring 2008 due to weather conditions this fall.

-          Metal railing.................................................................................... Completed

-          Bridge lighting............................................................................... Spring 2008

-          Bridge painting.............................................................................. Spring 2008

 

2.                  Champlin Drive

Work is completed with exception of seasonal landscaping and final wearing course. 

-          Landscaping (seasonal planting)..................................................... Spring 2008

-          Final Wearing Course................................................................... Spring 2008

 

3.                  Hayden Lake Road

A.  Hwy. 169 to Cobblestone Road

Work is completed with exception of one driveway that will be completed next spring.  Wood fencing, mailboxes, and final cleanup should be substantially complete by the November 30, 2007 with seasonal landscaping to be completed next spring.

-          Sodding.................................................................................... Completed

-          Landscaping (seasonal planting)............................................... Spring 2008

-          Final Wearing Course............................................................. Spring 2008

 

B.  Cobblestone Road to Tilden Avenue

Work is completed for this year, and the roadway is reopened to traffic.  The temporary park access route will be closed. 

-          Roadway Paving ........................................................ Reopened to Traffic

-          Temporary Turf and Erosion Control Establishment............ Late November

-          Sodding.................................................................................. Spring 2008

-          Trail and Sidewalk.................................................................. Spring 2008

-          Landscaping (seasonal plantings)............................................. Spring 2008

-          Final Wearing Course............................................................. Spring 2008

 

4.                  Tilden Avenue

Work on Tilden Avenue for this year is completed and will not be open for traffic.  Sidewalks and trails along with the remaining landscaping will be completed in spring 2008.

-          Roadway Embankment and Pond Construction............................... Completed

-          Turf and Erosion Control Establishment........................... Late November 2007

-          Concrete Curb and Gutter............................................................ Spring 2008

-          Roadway Paving........................................................................... Spring 2008

-          Sodding........................................................................................ Spring 2008

-          Landscaping................................................................................. Spring 2008

-          Final Wearing Course................................................................... Spring 2008

 

5.                  French Lake Road

The Contractor has completed the remaining underground utilities and roadway paved and reopened to traffic.  Trail and landscaping will be completed in spring 2008.

-          Roadway Paving.............................................................. Reopened for Traffic

-          Turf......................................................................................... Late November

-          Sodding........................................................................................ Spring 2008

-          Landscaping................................................................................. Spring 2008

-          Final Wearing Course................................................................... Spring 2008

 

6.                  Vera Street

All of the underground utility work and roadway have been completed.  The roadway is paved and reopened to local traffic.  The remaining sidewalk and retaining wall will be completed in the spring.

-          Roadway and Driveways Paved........................................ Reopened to Traffic

-          Erosion Control and Temporary Turf............................... Late November 2007

-          Sodding........................................................................................ Spring 2008

-          Sidewalk...................................................................................... Spring 2008

-          Final Wearing Course................................................................... Spring 2008

 

7.                  Business Park Drive (East Side of Hwy. 169)

The sanitary sewer work east of Hwy. 169 started on October 1 and will be completed by November 20, 2007.  The concrete sidewalk will be completed in spring 2008.

-          Roadway Patched and Reopened.................................................... Completed

-          Temporary Turf Reestablished............................................... By November 30

-          Sidewalks..................................................................................... Spring 2008

-          Seal Coat and Striping.................................................................. Spring 2008

 

II.    Project Success/Issues

 

1.                  Success

-          French Lake Road, Hayden Lake Road, and Vera Street reopened to Traffic by November 15, 2007.

-          French Lake Terrace Pond has recovered.

-          Cobblestone Lake Preserve water level recovered on October 5, 2007.

-          All City sewer, watermain, and storm sewer work completed.

-          All MCES sanitary sewer work completed.

-          Bridge complete with exception of lighting and painting.

-          Dewatering completed and removed.

-          All temporary water services removed.

 

2.                  Issues/Concerns

-          Currently, three residential claims unresolved:

a.       602 Hayden Lake Road (Dave Cochran) – Foundation crack

b.      10430 Creekwood Drive (CJ Hrebal) – Swimming pool and

      foundation cracks

c.       618 Hayden Lake Road – Foundation concerns

-          1113 Vera Street septic drain field repaired October 4, 2007.

-          Tilden Avenue will not be opened until mid to late June 2008.

 

III.  Contract Status/Changes

 

1.                  Contract Changes

-     Change Order No. 3 – Total pedestrian Signal Painting, and miscellaneous lighting repairs being finalized.

      a.   City - $3,199.22

      b.   County - $14,133.63

-     Change Order No. 4, December.  Fuel tank, miscellaneous storm sewer, water service connections, and MCES extra work approximately $71,000.

      a.   City anticipated $22,400 +

      b.   County anticipated $16,300 +

      c.   MCES anticipated $32,500 +

 

2.                  Contract Completion

-          Construction costs paid through October 31 = $11.63 million.

-          Anticipated construction costs spent through November = $12.63 million spent.

-          Anticipated October through December construction costs.

a.       November – $1.0 million

b.      December – $0.2 million

c.       Spring 2008 – $2.0 million

 

IV.   Project Web Page Update Reminder

 

V.     Questions/Answers