Daily
Construction Update
Area 1 & 2 - Contract 1- LaTour Construction, Inc
Inspector: Richard
Hjelle (651) 775-5112 Construction
Hotline: (651) 967-4501
·
Construction for the
day
-
Latour will be
installing trunk sanitary sewer along 134 ½ Ave. They will continue to the east
on 134 ½ Ave.
-
They will also
have a utility crew working on installing watermain on
-
North Pine will
work to grade
.
Area 3, 4 & 6 – Contract 2 – S.R. Weidema
Inspector: Katie
Kirchner (651) 755-3405 Construction Hotline: (651)
967-4512
·
Construction for
the day
-
Weidema will have
a utility crew working installing sanitary sewer on
-
They will also
have a utility crew working on
-
A road crew will
be working on
-
Another road crew
will work at the intersection of
-
The erosion
control crew will be out to repair and install new silt fence.
-
Another crew will
be working on testing sanitary sewer on
Area 5 – Contract 3 – Kuechle Underground
Inspector: Lance
Meyer (651)783-6582 Construction
Hotline: (651)967-4523
·
Construction for
the day
-
Curb and gutter
installation will continue on the remaining streets without curb.
-
Fehn will be
grading around finished driveways and boulevards in preparation for
hydroseeding.
-
Kuechle will be
installing mailboxes on curbed streets.
General
·
The schedule
above is an estimate for the day. The weather can delay the schedule or cause
it to change.
·
Please do not
hesitate to contact the inspectors if you have any questions about each
project. Paul Perez is also available to answer any questions or listen to
concerns at