Daily Construction Update
Area 1 & 2 - Contract 1- LaTour Construction, Inc
Inspector: Richard Hjelle
(651) 775-5112 Construction
Hotline: (651) 967-4501
·
Construction for the day
-
LaTour will have a utility crew working on storm sewer at
the intersection of South Diamond Lake Road Hemlock Lane. Once they finish they will move over and work on storm
sewer on
-
There will be
another utility crew on
-
Northpine will continue to haul in gravel in gravel on
Area 3, 4 & 6 – Contract 2 –
S.R. Weidema
Inspector: Katie Kirchner (651)
755-3405 Construction Hotline:
(651) 967-4512
·
Construction for the day
-
Weidema will have two utility crews on
-
One utility crew will work in
the morning to install drain tile on
-
They will also have a dirt crew
working on grading the boulevards on
-
McCrossan will be paving the rest of Vinewood later in the
afternoon.
Area 5 – Contract 3 – Kuechle Underground
Inspector: Lance Meyer (651)
783-6582 Construction Hotline:
(651) 967-4523
·
Construction for the day
-
McCrossan will be working on finishing the paving. Then they
will be working on asphalt driveways.
-
Creative Curb will possibly be
here to install concrete driveways.
General
·
The schedule above is an
estimate for the day. The weather can delay the schedule or cause it to change.
· Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.