Daily Construction Update

NE Dayton Areas 1-6 Street and Utility Improvements

October 30, 2007

 

Area 1 & 2 - Contract 1- LaTour Construction, Inc

Inspector: Richard Hjelle (651) 775-5112     Construction Hotline:  (651) 967-4501

·         Construction for the day

-        LaTour will have a utility crew working on storm sewer at the intersection of South Diamond Lake Road Hemlock Lane. Once they finish they will move over and work on storm sewer on 134th Ave.

-        There will be another utility crew on Zachary Circle installing water main and water services

-        Northpine will continue to haul in gravel in gravel on 134th Ave. They will also start to prepare 134th ½ Ave for gravel.

 

Area 3, 4 & 6 – Contract 2 – S.R. Weidema              

Inspector: Katie Kirchner (651) 755-3405      Construction Hotline: (651) 967-4512

·         Construction for the day

-        Weidema will have two utility crews on North Diamond Lake Road working on installing services.

-        One utility crew will work in the morning to install drain tile on Vinewood Lane they will then go back and work on North Diamond Lake Road

-        They will also have a dirt crew working on grading the boulevards on South Diamond Lake Road and Vinewood Lane.

-        McCrossan will be paving the rest of Vinewood later in the afternoon.

 

Area 5 – Contract 3 – Kuechle Underground

Inspector: Lance Meyer (651) 783-6582        Construction Hotline: (651) 967-4523

·         Construction for the day  

-        McCrossan will be working on finishing the paving. Then they will be working on asphalt driveways.

-        Creative Curb will possibly be here to install concrete driveways.

 

 

General

·         The schedule above is an estimate for the day. The weather can delay the schedule or cause it to change.

·        Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.