·         Construction for the day

-        LaTour will have a utility crew working on storm sewer at the intersection of Evergreen Lane and 136th Ave.

-        There will be another utility crew on Zachary Circle installing sanitary services.

-        Northpine will continue to spread topsoil in Area 1. They will also be hauling in gravel on 134th Ave.

 

Area 3, 4 & 6 – Contract 2 – S.R. Weidema              

Inspector: Katie Kirchner (651) 755-3405      Construction Hotline: (651) 967-4512

·         Construction for the day

-        Weidema will have two utility crews on North Diamond Lake Road working on installing services.

-        They will also have a dirt crew working on grading the boulevards on South Diamond Lake Road and Vinewood Lane.

-        The street crew will be backfilling curb and driveways on Vinewood Lane where curb was installed last week.

-        McCrossan will be paving the rest of South Diamond Lake Road.

 

Area 5 – Contract 3 – Kuechle Underground

Inspector: Lance Meyer (651) 783-6582        Construction Hotline: (651) 967-4523

·         Construction for the day  

-        Street crews will be placing gravel on the unpaved sections of the streets. Residents are to keep their cars off the graveled streets, so crews can finish preparing the gravel. McCrossan may be over later today to start to pave the graveled streets.

 

 

General

·         The schedule above is an estimate for the day. The weather can delay the schedule or cause it to change.