Daily Construction Update
Area 1 & 2 - Contract 1- LaTour Construction, Inc
Inspector: Richard Hjelle
(651) 775-5112 Construction
Hotline: (651) 967-4501
·
Construction for the day
-
LaTour will have a utility crew working on storm sewer on
-
There will be
another utility crew in the Evergreen area installing sanitary services.
-
There will be another utility
crew installing sanitary sewer on
-
Northpine will be spreading topsoil in Area 1. They will also
start to prepare 134th ½ Ave for gravel.
-
Friday Northpine
will work to prepare
-
McCrossan will pave
-
No work is scheduled for this
weekend
Area 3, 4 & 6 – Contract 2 –
S.R. Weidema
Inspector: Katie Kirchner (651)
755-3405 Construction Hotline:
(651) 967-4512
·
Construction for the day
-
Weidema will have a crew on
-
They will also have a utility
crew working
-
Street crews will be working to
prepare
-
They will start to pave at the intersection
of
-
They will continue to complete
culvert installation on
-
There is no work scheduled for
this weekend.
Area 5 – Contract 3 – Kuechle Underground
Inspector: Lance Meyer (651)
783-6582 Construction Hotline:
(651) 967-4523
·
Construction for the day
-
Street crews will be placing
gravel on the unpaved sections of the streets. Residents are to keep their cars
off the graveled streets, so crews can finish preparing the gravel. Paving will
start on Monday.
-
No work is scheduled for this
weekend.
General
·
The schedule above is an
estimate for the day. The weather can delay the schedule or cause it to change.
· Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.