Daily Construction Update
Area 1 & 2 - Contract 1- LaTour
Construction, Inc
Inspector: Richard Hjelle (651) 775-5112 Construction Hotline: (651) 967-4501
·
Construction for the day
-
Northpine will have
-
They will also have a utility
crew working on storm sewer on 134th1/2 Ave will be completed this
morning. They will be moving on to
-
There will be a
utility crew on
-
Paving on
-
Bituminous and concrete
driveways in Area 1 will resume tomorrow.
Area 3, 4 & 6 – Contract 2 –
S.R. Weidema
Inspector: Katie Kirchner (651)
755-3405 Construction Hotline:
(651) 967-4512
·
Construction for the day
-
Weidema will have a crew on
-
They will also have a utility
crew working on
-
Street crews will be working to
prepare
-
Schmidt Curb will be installing
curb on
-
Paving on
Area 5 – Contract 3 – Kuechle
Underground
Inspector: Lance Meyer (651)
783-6582 Construction Hotline:
(651) 967-4523
·
Construction for the day
-
Street crews will be placing
gravel on the unpaved sections of the streets. Residents are to keep their cars
off the graveled streets, so crews can finished the
tolerancing.
General
·
The schedule above is an
estimate for the day. The weather can delay the schedule or cause it to change.
· Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.