Daily Construction Update

NE Dayton Areas 1-6 Street and Utility Improvements

October 24, 2007

 

Area 1 & 2 - Contract 1- LaTour Construction, Inc

Inspector: Richard Hjelle (651) 775-5112     Construction Hotline:  (651) 967-4501

·         Construction for the day

-        Northpine will have South Diamond Lake Road from Evergreen Lane to Balsam Lane closed to work on grading the street. Residents who live to the south of South Diamond lake Road will have access from Arrowood lane and come in from the east. Residents who live on the north side of South Diamond Lake Road should access their neighborhood from Hemlock Lane and come in from the west.

-        They will also have a utility crew working on storm sewer on 134th1/2 Ave will be completed this morning. They will be moving on to Evergreen Lane to continue to install storm sewer.

-        There will be a utility crew on 134th Ave completing the installation of services on 134th Ave. Once that is complete they will move to Evergreen and work on service installation.

-        Paving on Balsam Lane is tentatively scheduled for tomorrow.

-        Bituminous and concrete driveways in Area 1 will resume tomorrow.

 

Area 3, 4 & 6 – Contract 2 – S.R. Weidema              

Inspector: Katie Kirchner (651) 755-3405      Construction Hotline: (651) 967-4512

·         Construction for the day

-        Weidema will have a crew on North Diamond Lake Road working on the water main installation.

-        They will also have a utility crew working on Pineview Lane installing water main on the west shoulder to the south of South Diamond Lake Road heading towards the water tower site.

-        Street crews will be working to prepare South Diamond Lake Road and Vinewood Lane for bituminous pavement. Paving is scheduled for tomorrow.  

-        Schmidt Curb will be installing curb on Vinewood Lane north of 139th Ave.

-        Paving on South Diamond Lake Road, Vinewood Lane and 139th Ave are scheduled to begin tomorrow.

 

 

Area 5 – Contract 3 – Kuechle Underground

Inspector: Lance Meyer (651) 783-6582        Construction Hotline: (651) 967-4523

·         Construction for the day  

-        Street crews will be placing gravel on the unpaved sections of the streets. Residents are to keep their cars off the graveled streets, so crews can finished the tolerancing.

 

 

General

·         The schedule above is an estimate for the day. The weather can delay the schedule or cause it to change.

·        Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.