Daily Construction Update

NE Dayton Areas 1-6 Street and Utility Improvements

October 23, 2007

 

Area 1 & 2 - Contract 1- LaTour Construction, Inc

Inspector: Richard Hjelle (651) 775-5112     Construction Hotline:  (651) 967-4501

·         Construction for the day

-        Northpine will have South Diamond Lake Road from Evergreen Lane to Balsam Lane closed to work on grading the street. Residents who live to the south of South Diamond lake Road will have access from Arrowood lane and come in from the east. Residents who live on the north side of South Diamond Lake Road should access their neighborhood from Hemlock Lane and come in from the west.

-        They will also have a utility crew working on storm sewer on 134th1/2 Ave.

-        Another utility crew will be working on completing water main installation and then start water services.

-        Another utility crew will also be installing sanitary sewer on Zachary Circle.

-        They will also  start to install bituminous and concrete driveways in Area 1 to the south of the golf course.

 

Area 3, 4 & 6 – Contract 2 – S.R. Weidema              

Inspector: Katie Kirchner (651) 755-3405      Construction Hotline: (651) 967-4512

·         Construction for the day

-        Today, Weidema will have a utility crew working installing sanitary sewer stub on North Diamond Lake Road. They will then start to install water main at the intersection of North Diamond Lake Road and Vinewood Lane. They will continue to the north and then head west down North Diamond Lake Road. Residents who live on Vinewood Lane will need to exit and come in from the South Diamond Lake Road. Residents who live on North Diamond Lake Road will need to come in from the west until they get passed their homes as they work from east to west. The water main installation is a faster process than the sanitary sewer installation.

-        They will also have a utility crew working on Pineview Lane installing water main on the west shoulder to the south of South Diamond Lake Road heading towards the water tower site.

-        Street crews will be working to prepare the intersection of South Diamond Lake Road and Pineview Lane for bituminous pavement.

 

 

Area 5 – Contract 3 – Kuechle Underground

Inspector: Lance Meyer (651) 783-6582        Construction Hotline: (651) 967-4523

·         Construction for the day  

-        Today, crews will be working on cleaning up the streets. They will work on grading boulevards and preparing driveways for asphalt or concrete.

 

 

General

·         The schedule above is an estimate for the day. The weather can delay the schedule or cause it to change.

·        Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.