Daily
Construction Update
Area 1 & 2 - Contract 1- LaTour Construction, Inc
Inspector: Richard
Hjelle (651) 775-5112 Construction
Hotline: (651) 967-4501
·
Construction for the
day
-
Latour is working
on installing sanitary sewer on 134 Ave.
-
They also have a utility crew working on storm
sewer on
-
Once the storm
sewer is installed they will move into the Evergreen Area, north of
-
North Pine will
work to grade the ditches
.
Area 3, 4 & 6 – Contract 2 – S.R. Weidema
Inspector: Katie
Kirchner (651) 755-3405 Construction Hotline: (651)
967-4512
·
Construction for
the day
-
Weidema will have
a utility crew working installing sanitary sewer on
-
They will be
working on pumping water out of streets and grading out rough streets.
-
They will also be
installing the property owner’s fence along the sanitary easement to the east
of
Area 5 – Contract 3 – Kuechle Underground
Inspector: Lance
Meyer (651)783-6582 Construction
Hotline: (651)967-4523
·
Construction for
the day
-
Kuechle will be
raising manholes castings on all of the paved streets.
-
Kuechle will also
be saw cutting and removing damaged driveway sections on the newly curbed
streets.
General
·
Today’s rain fall may shut down crews early.
·
The schedule
above is an estimate for the day. The weather can delay the schedule or cause
it to change.
·
Please do not
hesitate to contact the inspectors if you have any questions about each
project. Paul Perez is also available to answer any questions or listen to
concerns at