Daily Construction Update

NE Dayton Areas 1-6 Street and Utility Improvements

November 7, 2007

 

Area 1 & 2 - Contract 1- LaTour Construction, Inc

Inspector: Richard Hjelle (651) 775-5112     Construction Hotline:  (651) 967-4501

·         Construction for the day

-        LaTour will be installing water main in the Dayton Industrial Park east of Balsam Lane.

-        Northpine will be sub-cutting in the Evergreen Area preparing it for gravel, and tolerancing French lake road for paving.

-        Latour is installing trunk sewer thru the Hayden Hills Golf Course. Beginning at the intersection of Deerwood and Balsam and working to the north.

-        Creative Curb is setting up string line for curb Thursday.

 

Area 3, 4 & 6 – Contract 2 – S.R. Weidema              

Inspector: Katie Kirchner (651) 755-3405      Construction Hotline: (651) 967-4512

·         Construction for the day

-        Road crews will be hauling in gravel on North Diamond Lake Road and preparing it for bituminous pavement for tomorrow.

-        They will also work on preparing driveways for bituminous.

 

 

Area 5 – Contract 3 – Kuechle Underground

Inspector: Lance Meyer (651) 783-6582        Construction Hotline: (651) 967-4523

·         Construction for the day   

-        No work is scheduled for today.

 

 

General

·         The schedule above is an estimate for the day. The weather can delay the schedule or cause it to change.

·        Please do not hesitate to contact the inspectors if you have any questions about each project. Paul Perez is also available to answer any questions or listen to concerns at (651) 324-5585.