Daily Construction Update
November 20, 2007
Area 1 & 2 - Contract 1- LaTour Construction, Inc
Inspector: Richard Hjelle
· Construction for the day
-
LaTour will be installing sanitary sewer and water main
through Hayden Hills Golf Course.
-
Northpine will be preparing driveways on both areas of the
project.
-
McCrossan will be paving
Area 3, 4 & 6 – Contract 2 –
S.R. Weidema
Inspector: Katie Kirchner
·
Construction for the day
-
Weidema will continue to seed throughout the project for the
rest of the week.
-
They will continue to grade the
ditches on
Area 5 – Contract 3 – Kuechle
Underground
Inspector: Lance Meyer
·
Construction for the day
-
Kuechle will be raising the
manhole castings throughout the project the rest of the week.
General
·
The schedule above is an
estimate for the day. The weather can delay the schedule or cause it to change.
·
Please do not hesitate to
contact the inspectors if you have any questions about each project. Paul Perez
is also available to answer any questions or listen to concerns at