Construction Update

NE Dayton Areas 1-6

Street and Utility Improvements

August 1, 2007

 

 

Area 1 & 2 - Contract 1- LaTour Construction, Inc

 

·        Construction Status

-       Work done to date

o       Latour has completed all pipe work south of the golf course with the exception of Zachary Circle

o       All roads are have Curb and Gutter south of the golf course with the exception of Zachary Circle

o       Latour is continuing with sanitary sewer in Evergreen north of South Diamond Lake Road

o       Latour is installing watermain and storm sewer on Balsam Lane and South Diamond Lake Road.

-       Work anticipated in the next week

o       Latour will be finishing up sanitary sewer in the Evergreen Area north of South Diamond Lake Road.  Completion of water main in Balsam and continue with storm sewer in South Diamond Lake Road.

o       Northpine Aggregate will be ramping in driveways and start tolerance streets for paving south of the golf course.

.

Area 3, 4 & 6 – Contract 2 – S.R. Weidema

·        Construction Status

-       Work done to date

o       The curb and gutter has been installed on Noon Drive and Jonquil Lane. The bituminous base course has also been installed.

o       Sanitary sewer installation has been completed on South Diamond Lake Road and they have started to install water main and have completed up to Vinewood Lane.

o       The sanitary sewer and water main installation on Vinewood Lane, north of 139th Ave has been completed. Half of the services have been installed.

o       All of the utilities are installed on 139th Ave.

-       Work anticipated in the next week

o       They will start to bring in topsoil on Noon Drive and Jonquil Lane. Driveway installation will be start later next week.

o       On Vinewood Lane they will continue to install sewer and water services. Once all the services are installed they will start to grade the road for gravel and install the culverts.

o        On 139th Ave they will start grading out the road and get it ready for gravel.

o       Curb and gutter installation for Vinewood Lane is scheduled for middle of next week.

o       Starting next Monday, October 1, 2007 they will start to mill on North Diamond Lake Road. The utility installation will follow. The road will be closed and the detour should be utilized.

o       By the end of next week South Diamond Lake Road will be graveled from Vinewood Lane to Pineview Lane.  They will continue  to work to the west getting the road ready for gravel.

 

Area 5 – Contract 3 – Kuechle Underground

·        Construction Status

-       Work done to date

o       All pipe work has been installed on the project with the exception of the storm sewer pipe that extends to the Mississippi River which will be installed during the later part of this week.

o       Driveways on the paved portions of the project will be saw cut and removed in preparation for driveway paving which will happen at the end of this week and next.

 

-       Work anticipated in the next week

o       Curb and gutter will be poured on Pineview Tr, Oakview Ln, Magnolia Ln, Norwood Ln, and 140th Ave.

o       Driveways on curbed portions of the project will be re-paved.

o       Mailboxes will be re-installed

o       Hydroseeding will begin on finished sections.