Construction
Update
Street and
Utility Improvements
Area 1 & 2 - Contract
1- LaTour Construction, Inc
·
Construction
Status
-
Work done to date
o
Latour has
completed sanitary sewer on Deerwood up to
o
A second crew for
Latour worked on sanitary sewer and water main up
o
A third crew for
Latour started storm sewer on
o
Northpine
Aggregate reclaimed the roadway on
o
Northern
Dewatering began dewatering on
-
Work anticipated
in the next week
o
Storm sewer will
continue to be installed on
o
Latour will begin
installing storm sewer on
o
Northpine
Aggregate will be putting gravel on
.
Area 3, 4 & 6
– Contract 2 – S.R. Weidema
·
Construction
Status
-
Work done to date
o
The dirt crew on
o
The sanitary
sewer and water main installation on
o
The directional
drilling on
o
Sanitary sewer
and water main has been completed up to
-
Work anticipated
in the next week
o
o
They will
continue to install sanitary sewer between City Hall and Dayton Elementary.
They continue to install along the soccer fields and head west through the
easement to
o
They will also
continue to directional drill water main
o
A utility crew
will continue to install sanitary sewer and water main on
Area 5 – Contract
3 – Kuechle Underground
·
Construction
Status
-
Work done to date
o
All sanitary
sewer installation on the milled streets (141st, Rosewood,
Quinnwood, Overlook) is complete.
o
All water main installation
on the milled streets is complete.
o
All storm sewer
installation on the milled streets is complete except for the portion on
o
The milled
streets will be getting class 5 aggregate on them this week in preparation for
the curb and pavement.
o
All pipe work in
-
Work anticipated
in the next week
o
Sanitary sewer
will be installed up
o
Water main will
be installed on
o
Services on
Pineview will be installed next week.
o
There is a
possibility of curb and gutter installation next week on
o
Storm sewer will
be installed this week on
Well No. 2 -
·
Land Acquisition
-
The paperwork has
been sent to Gold Nugget, Inc., and once the land is acquired the well
construction will begin.
-
Preconstruction
Meeting was held on
·
Construction
Status
-
No work has been
completed
0.5 MG Water Tower
–
·
LandMark has completed
pouring the tower foundation slab.
-
Mobilization of
construction trailers has been completed.
-
Land Mark
delivered concrete forms and steel reinforcing.
-
The first
foundation wall pour occurred on Thursday July 26.